- Application Form
- To apply online for Drainage Connection click here
- To download and view Drainage Regulation Act 1990 please click on links given below
- The Corporation provides facility of drainage connection in certain estates only. Please confirm with respective GIDC field office for availability of infrastructure.
- Documents Checklist
- The following documents should be kept ready and submitted along with the duly filled up application form of Drainage Connection.
- Editable application form (Adhesive stamp of Rs. 300)
- Copy of Offer cum Allotment letter
- Copy of Approved Building Plans with letter
- Copy of Licence Agreement / Form of Agreement
- Approved primary ETP/STP plan by GPCB and certificate of installation
- If Industrial unit – Copy of GPCB NOC + Copy of application made to GPCB
- Water supply connection details (location of connection, quantity, size of connection etc.)
- Water supply bills – Last 3 months (not mandatory)
- Possession Receipt and /OR Final Transfer Order (Mandatory)
Note : If necessary, GIDC will ask the applicant to submit other necessary documents to process the application.
- The following documents should be kept ready and submitted along with the duly filled up application form of Drainage Connection.
- Scrutiny Procedure
The following verification is carried out by GIDC before providing approval and connection to applicant
- If building plan is approved
- Whether quantity applied for same in License Agreement/ Form of Agreement, GPCB NOC and mentioned in the application
- If difference, then what is the reason (A query may be raised to the applicant in such case)
- Scrutiny of NOC from GPCB
- Verify that drainage connection can be given from the existing drainage line on facing road at distance
- Whether allottee has been allowed to use treated water into garden or any other use/recycling/another disposal
- Visits the site to fix the location of drainage chamber, verify the free fall arrangements in drainage connection chamber
- Provides schematic diagram of connection from drainage mains to connection chamber, size of connection, and calculation of drainage connection charges, deposits, contribution charges to applicant
Note : Ideal time for processing a Drainage application without any queries post physical submission of application form and required documents at respective DEE office is as below.
No. | Process | Ideal time |
---|---|---|
1 | Providing approval for connection | 10 days from date of application |
2 | Providing physical connection on site | Max 20 days from date of approval application (Provided all the formalities are completed by the Allottee) |
Remarks : The procedural steps outlined above are uniform, consistent, and applicable across all types of establishments, regardless of their risk category, firm size/category (small, medium, large), business location (whether rural or urban), and the type of investor (whether foreign or domestic).